The following pictures of Jinjang MRT station taken during the construction. Click to view from beginning.
📅 November 2021
Testing of ticket vending machine at the concourse level of the Jinjang MRT Station.
![Testing of ticket vending machine at the concourse level of the Jinjang MRT Station](/wp-content/uploads/2021/10/jinjang-mrt-station-2021-11-nov-01.webp)
Credits: mymrt.com.my.
📅 October 2021
Aerial view of the Jinjang MRT Station showing the rectification works for defects list in progress.
![Aerial view of the Jinjang MRT Station showing the rectification works for defects list in progress](/wp-content/uploads/2021/10/jinjang-mrt-station-2021-10-oct-01.webp)
Aerial view of the at-grade park and ride Jinjang MRT Station showing the rectification works for defects list in progress.
![Aerial view of the at-grade park and ride Jinjang MRT Station showing the rectification works for defects list in progress](/wp-content/uploads/2021/10/jinjang-mrt-station-2021-10-oct-02.webp)
Testing of automatic fare collection gate system in progress at the Jinjang MRT Station.
![Testing of automatic fare collection gate system in progress at the Jinjang MRT Station](/wp-content/uploads/2021/10/jinjang-mrt-station-2021-10-oct-03.webp)
Credits: mymrt.com.my.
📅 September 2021
Site tidiness works in progress at the Jinjang MRT Station at-grade park and ride.
![Site tidiness works in progress at the Jinjang MRT Station at-grade park and ride](/wp-content/uploads/2021/10/jinjang-mrt-station-2021-09-sep-01.webp)
Imprint works in progress at the Jinjang MRT Station.
![Imprint works in progress at the Jinjang MRT Station](/wp-content/uploads/2021/10/jinjang-mrt-station-2021-09-sep-02.webp)
Credits: mymrt.com.my.
📅 August 2021
Aerial view of the Jinjang MRT Station.
![Aerial view of the Jinjang MRT Station](/wp-content/uploads/2021/11/jinjang-mrt-station-august-2021-01-768x512.webp)
View of the connected link bridge.
![View of the connected link bridge](/wp-content/uploads/2021/11/jinjang-mrt-station-august-2021-02-768x512.webp)
Credits: mymrt.com.my.
📅 July 2021
Aerial view of the Jinjang MRT Station showing the defect rectification works in progress.
![Aerial view of the Jinjang MRT Station showing the defect rectification works in progress](/wp-content/uploads/2021/11/jinjang-mrt-station-july-2021-01-768x512.webp)
Credits: mymrt.com.my.
📅 April 2021
View inside the Jinjang MRT Station showing the site cleaning in progress for handing over to the operator, Rapid Rail.
![View inside the Jinjang MRT Station showing the site cleaning in progress for handing over to the operator, Rapid Rail](/wp-content/uploads/2021/10/jinjang-mrt-station-april-2021-01-768x512.webp)
Credits: mymrt.com.my.
📅 February 2021
Aerial view of the Jinjang MRT Station showing the asphaltic concrete wearing course laying completed.
![Aerial view of the Jinjang MRT Station showing the asphaltic concrete wearing course laying completed](/wp-content/uploads/2021/10/jinjang-mrt-station-february-2021-01-768x512.webp)
Road and drainage works completed at the At-Grade Park and Ride for Jinjang MRT Station.
![Road and drainage works completed at the At-Grade Park and Ride for Jinjang MRT Station](/wp-content/uploads/2021/10/jinjang-mrt-station-february-2021-02-768x512.webp)
Credits: mymrt.com.my.
📅 January 2021
Aerial view of the Jinjang MRT Station showing the pier repair for finishes in progress.
![Aerial view of the Jinjang MRT Station showing the pier repair for finishes in progress](/wp-content/uploads/2021/10/jinjang-mrt-station-january-2021-01-768x512.webp)
Premix works in progress at the At-Grade Park and Ride for Jinjang MRT Station.
![Premix works in progress at the At-Grade Park and Ride for Jinjang MRT Station](/wp-content/uploads/2021/10/jinjang-mrt-station-january-2021-02-768x512.webp)
External mural painting works in progress at the Jinjang MRT Station.
![External mural painting works in progress at the Jinjang MRT Station](/wp-content/uploads/2021/10/jinjang-mrt-station-january-2021-03-768x355.webp)
Line marking works in progress at the At-Grade Park and Ride for Jinjang MRT Station.
![Line marking works in progress at the At-Grade Park and Ride for Jinjang MRT Station](/wp-content/uploads/2021/10/jinjang-mrt-station-january-2021-04-768x512.webp)
Credits: mymrt.com.my.
📅 November 2020
Inside view of the Jinjang MRT Station site showing the mural painting at lift concourse level works in progress.
![Inside view of the Jinjang MRT Station site showing the mural painting at lift concourse level works in progress](/wp-content/uploads/2021/10/jinjang-mrt-station-november-2020-01-768x512.webp)
Credits: mymrt.com.my.
📅 October 2020
Aerial view of the Pedestrian Overhead Bridge Jinjang MRT Station showing the walkway and apron slab works in progress at Entrance 2.
![Aerial view of the Pedestrian Overhead Bridge Jinjang MRT Station showing the walkway and apron slab works in progress at Entrance 2](/wp-content/uploads/2021/10/jinjang-mrt-station-october-2020-01-768x512.webp)
Credits: mymrt.com.my.
📅 September 2020
Aerial view of the Jinjang MRT Station site showing the station external works in progress such as roadworks.
![Aerial view of the Jinjang MRT Station site showing the station external works in progress such as roadworks](/wp-content/uploads/2021/10/jinjang-mrt-station-september-2020-01-768x512.webp)
Automatic Platform Gate installed and completed at the Jinjang MRT Station.
![Automatic Platform Gate installed and completed at the Jinjang MRT Station](/wp-content/uploads/2021/10/jinjang-mrt-station-september-2020-02-768x512.webp)
Credits: mymrt.com.my.
Hawk-eye View
Location of Jinjang MRT Station and its surrounding area.
![Location of Jinjang MRT Station and its surrounding area](/wp-content/uploads/2021/11/jinjang-mrt-station-hawk-eye-view-1088x653.webp)
Credits: mymrt.com.my.
★ ★ Back to Jinjang MRT station.