The following pictures of Bandar Malaysia Selatan MRT station taken during the construction .
Main entrance at the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Overview of the Bandar Malaysia Selatan MRT Station Entrance A.

Cleaning works of the Electrical and Mechanical equipment in progress at the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Louvres installation in progress at the Bandar Malaysia Selatan MRT Station Entrance B.

Apron slab construction works in progress at the Bandar Malaysia Selatan MRT Station Entrance B.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station.

Louvres installation in progress at the Bandar Malaysia Selatan MRT Station Entrance B.

Photo Credits: mymrt.com.my.
Sprinklers, hose reel, tank and pump room completed at the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Turfing and external plastering works for Bandar Malaysia Selatan MRT Station entrance in progress.

Low Voltage Room at the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
External plastering works in progress at the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station showing the entrance structure works, backfilling and road works in progress.

View of the Bandar Malaysia Selatan MRT Station showing the entrance structure works, backfilling and road works in progress.

Photo Credits: mymrt.com.my.
Ceiling fibreboard installation works in progress at the concourse level of the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station showing the backfilling, above ground structures and drainage works in progress.

Electrical and mechanical works in progress at the Tunnel Ventilation System Motor Control Centre (TVS MCC) Room 2 of the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station showing backfilling works and above ground structures works in progress.

Construction of the entrance and ventilation building of the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
View of the Bandar Malaysia Selatan MRT Station showing the platform drywall installation works in progress.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station showing the Entrance B ground level and level one works.

View of the Bandar Malaysia Selatan MRT Station showing drywall installation and painting works in progress at the platform level.

Photo Credits: mymrt.com.my.
View of the Bandar Malaysia Selatan MRT Station showing the concourse slab rebar installation works in progress at the Entrance A.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station.

View of the Bandar Malaysia Selatan MRT Station showing the installation of uninterruptible power supply (UPS) module in progress at the concourse level UPS room.

Photo Credits: mymrt.com.my.
Cable laying and distribution box installation works in progress at the Distribution Box Room 3, Platform Level of the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Rectification works after the casting of reinforced concrete wall in progress at the station box of the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station showing the ongoing secant bored piles construction works at the remaining section of Entrance A.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station showing the reinforced concrete works for platform and concourse level progressing well concurrently with electrical and mechanical works and architecture fitouts.

Preparation for concrete casting of internal wall at the concourse level of the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station showing the reinforced concrete works for platform and concourse level in progress.

Photo Credits: mymrt.com.my.
View of the Bandar Malaysia Selatan MRT Station showing the preparatory works for roof slab casting in progress. Jet grouting works completed on early November 2020.

Photo Credits: mymrt.com.my.
View of the Bandar Malaysia Selatan MRT Station showing the crossover roof slab water proofing works in progress and suitable backfill materials is stockpiled at site while preparing the temporary works for roof slab casting.

Preparatory works for platform slab casting is in progress at the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
View of the Bandar Malaysia Selatan MRT Station site showing completion at 72.5% as end of September 2020.

Platform slab reinforced concrete works for southbound traction power substation and 33kv rooms at the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station site showing the station box and site laydown.

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station site showing the station box and site laydown.

Falsework in place for reinforced concrete works to proceed to close the current temporary openings at the Bandar Malaysia Selatan MRT Station site

Photo Credits: mymrt.com.my.
Aerial view of the Bandar Malaysia Selatan MRT Station.

Roof slab falsework in place for reinforcement concrete works inside the Bandar Malaysia Selatan MRT Station.

Photo Credits: mymrt.com.my.
Falsework for roof slab being installed and inspected at the Bandar Malaysia Selatan MRT Station site.

Photo Credits: mymrt.com.my.
Aerial view of the station box at the Bandar Malaysia Selatan MRT Station site.

Reinforcement works for internal wall in progress at the Bandar Malaysia Selatan MRT Station site.

Photo Credits: mymrt.com.my.
Reinforced wall formwork removal in progress at the Bandar Malaysia Selatan MRT Station site.

Photo Credits: mymrt.com.my.
Base slab excavation and levelling works in progress at the Bandar Malaysia South MRT Station.

Aerial view of the Bandar Malaysia Selatan MRT Station site showing the ongoing station box excavation.

Photo Credits: mymrt.com.my.